A $6.4 million overlay project is set to begin on US 287 in Clarendon on April 1.
The project will include all lanes in the city as well as the southbound lanes from Clarendon to the Armstrong County line. The contractor for the project is J Lee Milligan.
TxDOT spokesperson Ginger Wilson said the work in Clarendon will consist of grinding off the top surface of the asphalt and putting down a new finish.
Drivers can expect daily lane closures during the project and are reminded to use caution when traveling through the work zone. This includes reducing your speed, obeying all posted warnings, and avoiding all distractions. Fines double in work zones when workers are present.
Work in the town section is expected to take six weeks to complete, weather pending.
For more information, contact Ginger.Wilson@txdot.gov or (940) 937-7288.